Valpo to begin 2nd phase of Bicentennial Park work

2013-03-03T17:30:00Z 2013-03-03T19:57:28Z Valpo to begin 2nd phase of Bicentennial Park workPhil Wieland phil.wieland@nwi.com, (219) 548-4352 nwitimes.com

VALPARAISO | The second phase of the transformation of Bicentennial Park begins this week with the parks department seeking quotes for installing drainage improvements at the park.

The makeover of the park started in 2012 with reconstruction of the adult softball field on the west side of the park into a youth and girls softball field. Sewer and electric lines also were laid in preparation for building a concession stand next to the field just south of the parking area. The existing restrooms will be moved to the concession building. Total cost of the first phase was $73,000.

The drainage work is estimated to cost $130,000 and will include bioswales and rain gardens and a drainage outlet extending across Campbell Street to a detention area to the west. Parks Director John Seibert said drainage problems have worsened as the area around the park has developed.

"It doesn't solve all the drainage problems we have now, but we will be able to tie in to the drainage improvements to be made on Burlington Beach Road in the future," Seibert said. "We are taking the water from where it is to where we want it to be, and it will not be in the traffic patterns."

The first phase was funded with money from the city budget. The second phase is getting $75,000 from the utilities board from the stormwater budget and $25,000 from the city. The remaining money will have to come from the parks budget or some other source, which is why Seibert said he's hoping the cost is less than the estimate.

Seibert said the goal is to get the work done in May so the park will be ready for the softball season. By that time a decision might also be made on the fate of the tennis courts at the park. Parks officials tentatively have planned to spend about $10,000 this year to make cosmetic improvements, such as painting the fence, but the board must decide whether to keep the courts or use the space for parking or something else.

Keeping the courts could mean paying $150,000 to rebuild them, an expense that could be hard to meet. The third phase of the park improvements, planned for 2014, already includes replacing the playground equipment, building the concession stand and restroom facilities and expanding and improving the parking area.

The final phase in 2015 calls for reconfiguring the east softball field and, if funding is available, adding the third field. A new picnic shelter area is planned along with hardscape paths to make it easier for people in wheelchairs or pushing strollers to reach all the park facilities.

"Our emphasis with limited money — safety has been the highest priority and accessibility and youth sports are second," Seibert said. "We can't fully fund these projects, so the reality is we have to do them in phases."

Copyright 2013 nwitimes.com. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Follow The Times

Facebook

on Facebook

Twitter

on Twitter

Email

Get email updates from

Email Updates

RSS

Follow via RSS

RSS Feeds

Latest Local Offers

All Services Electric
$100 off any generator purchase

One coupon per customer, not applicable with any other discoun…

Allied Health Institute
Save $100 & no registration fee at Allied Health Institute.

Call 219-793-1111 for more details.  www.alliedhealthnwi.com

Grieger's Motor Sales Inc
Chrysler Certified: 7yr/100k mi powertrain limited warranty, 3month/3k mi maximum care coverage.

 See dealer for details. (888)360-8519   www.griegermotor…

For those who want something truly unique we offer custom jewelry design.

Whether you already have a drawing in hand or only an idea in …

All Services Electric
Free Surge Protector with every generator purchase.

One coupon per customer, not applicable with any other discoun…

Featured Businesses

National Video

Poll

Loading…

Do you cooperate with colleagues across the state line when working on a major regional project?

View Results

Porter County Videos

Home Sweet Home

Blake Loudenber is an inspiration. After 28 days at the University of Chicago Medicine Comer Children's Hos…

A Miracle For Blake

A Miracle For Blake

Nine-year-old Blake Loudenber was born with polycystic kidney disease. He has been waiting …

Raw video: Demolition begins of charred building

Raw video: Demolition begins of charred building

Demolition crews began dismantling a large building in downtown Valparaiso that caught fire …

Newsletter Sign-Up